Project Update
February 9: Continuation of Storm Water mitigation installations, start of equipment staging and start of dismantling the railing along the South Shoreline are the most significant field activities this week. Administrative accomplishments include City conditional permit approval allowing pile driving to start on the 20th. Responses to the City’s permit review comments and questions is ongoing.