Project Update
January 26: The contractor continued to construct the promenade deck falsework and formwork to support the construction of the new concrete deck moving near the future Gate F terminal. They also began installing the rebar for the promenade deck canopy beam and completed placement of the first reinforced concrete deck section for the promenade. In preparation for future work additional rebar, falsework and scaffolding was delivered to the project. Over the next several weeks the contractor’s crews are scheduled to continue installing promenade deck falsework/formwork, install concrete deck embeds/rebar, install pile rebar cages in the lagoon area, place concrete for the promenade canopy beam and place concrete for the next section of promenade deck.