Project Update
August 17, 2018: This week the contractor continued installation of formwork and rebar for Deck Pour #11 on the North side of the lagoon. The contractor also successfully placed concrete in the remaining 24 inch piles in the lagoon. At the promenade, the subcontractors began the installation of the doors at Gate F and continued the installation of electrical conduits at Gate G.
Over the next several weeks, the contractor is scheduled to continue work on formwork along the Ferry Building, begin work on the falsework in the middle of the lagoon, drive foundation piles for the promenade, and install the portals at Gate F and Gate G. Subcontractors are scheduled to place rebar for Deck Pour #11 and Deck Pour #14 and continue work on the curbs around the promenade.