Project Update
March 8, 2019: This week work continued in the plaza. The contractor continued to place plywood for the cold joint between Deck Pour #16 and Deck Pour #17 and began placing formwork for the stairs. The rebar subcontractor finished installing rebar for Deck Pour #16 and the contractor successfully placed concrete for Deck Pour #16 in the lagoon.
Demolition also continued at the existing Gate E. The contractor continued removing handrails and section of guardrail from the Gate E float and gangway and removed the existing Gangway from Gate E.
Over the next several weeks, the contractor is scheduled to place falsework and formwork for Deck Pour #17 in the plaza, pour concrete for Deck Pour #17, continue the demolition of Gate E; including the removal of the float, and complete punch list items related to Gates F & G.