The Downtown San Francisco Ferry Terminal Expansion Project

Project Home | Background | Environmental Review | Construction | Outreach | Updates

Project Update

March 8, 2019: This week work continued in the plaza.  The contractor continued to place plywood for the cold joint between Deck Pour #16 and Deck Pour #17 and began placing formwork for the stairs. The rebar subcontractor finished installing rebar for Deck Pour #16 and the contractor successfully placed concrete for Deck Pour #16 in the lagoon.
 
Demolition also continued at the existing Gate E. The contractor continued removing handrails and section of guardrail from the Gate E float and gangway and removed the existing Gangway from Gate E.
 
Over the next several weeks, the contractor is scheduled to place falsework and formwork for Deck Pour #17 in the plaza, pour concrete for Deck Pour #17, continue the demolition of Gate E; including the removal of the float, and complete punch list items related to Gates F & G.

Project Update

March 1, 2019: This week the contractors and their subcontractors continued work in the Plaza. The contractor began to place plywood for the cold joint between Deck Pour #16 and Deck Pour #17. The surveying subcontractor continued surveying the plaza stairs, while the rebar locating subcontractor began locating rebar in the steps of the Plaza.
 
Demo continued at the existing Gate E with the contractor removing handrails and a section of guardrail from the Gate E float and gangway. The contractor also continued removing the pile caps from the guide piles around the Gate E float. Also at the Gate E portal the contractor began removing sections of granite that made up the compass on the west side of the Portal.

Over the next several weeks, the contractor is scheduled to place falsework and formwork for Deck Pour #17 in the plaza, pour concrete for the Deck Pour #16, continue demo of Gate E, and complete punch list items related to Gates F & G.

Project Update

February 22: This week the contractor continued to place aluma beams, plywood and bottom mat of rebar for Deck Pour #16 and began stripping the soffit forms from Deck Pour #15.
 
Demo began at the existing Gate E this week. The contractor began removing handrails and section of guardrail from the Gate E float and gangway and began removing the pile caps from the guide piles around the Gate E float. 
 
Over the next several weeks, the contractor is scheduled to place falsework and formwork for Deck Pour #17 in the plaza, pour concrete for Deck Pour #16, continue the demo of Gate E, and complete punch list items related to Gates F & G.
 

Project Update

February 22, 2019: This week the contractor continued to place aluma beams, plywood and bottom mat of rebar for Deck Pour #16 and began stripping the soffit forms from Deck Pour #15.
 
Demo began at the existing Gate E this week. The contractor began removing handrails and section of guardrail from the Gate E float and gangway and began removing the pile caps from the guide piles around the Gate E float.
 
Over the next several weeks, the contractor is scheduled to place falsework and formwork for Deck Pour #17 in the plaza, pour concrete for Deck Pour #16, continue the demo of Gate E, and complete punch list items related to Gates F & G.

Project Update

February 15, 2019: This week work on Gate F continued, including power washing and cleaning the float and gangway and touchup paint on the piles, pile collars, float, gangway, fenders on the Gate F float, and the promenade canopy. The electrical sub completed their last installations of lights on the Gate F Portal, while the contractor finished installing stainless corner pieces on the Gate F Portal pedestal. The glazing subcontractor was onsite installing waterproofing on the promenade canopy. The metal subcontractor continued to install soffit panels on the Gate F and Gate G Portal Canopies. The paint subcontractor was onsite to paint the traditional handrail on the promenade. In the lagoon, the contractor began installing the falsework for Deck Pour #16.

Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, and completing punchlist items related to the Section 1 opening.

Project Update

February 8, 2019: This week work on Gate F Terminal continued, including sanding and staining the top rails on the float and gangway and paint touch-ups on the pile collars and fenders. Additionally, the electrical subcontractor began installing conduit in the portal canopy at Gate G for the electronic real-time sign, the glazing subcontractor was onsite installing waterproofing on the promenade canopy, and the metal subcontractor continued to install soffit panels on the Gate F portal and began preparations for the install of soffit panels on the Gate G portal. In the lagoon, the contractor began installing the falsework for Deck Pour #16.
 
Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, continue work related to opening Gate F, and continue work on the punch list items related to the opening of the promenade.

Project Update

February 1, 2019: This week work on Gate F continued as the contractor began sanding and staining the top rails on the float and gangway and the electrical sub began installing conduit in Deck Pour #15 for the light posts in the lagoon. The glazing subcontractor was onsite installing waterproofing on the promenade canopy and the metal subcontractor installed the letters on the Gate F portal and began the installation of the portal canopy soffit panels. In the lagoon, the rebar subcontractor was onsite to continue installing rebar for Deck Pour #15, and the contractor successfully poured Deck Pour #15.
 
Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, continue work related to Terminal F operational, and completing punch list items related to Gate G gangway and float.

Project Update

January 25, 2019: This week work continued on Gate F as the contractor began tack welding the pins on the gangway bushing plates, installing electrical equipment in the electrical cabinets and installing, sanding, and staining the wood top rail. The metal subcontractor also began installing the letters on the Gate F portal canopy and began prepping the portal canopy soffit panels for installation. In the lagoon, the contractor continued setting side forms Deck Pour #15, while also stripping soffit forms from Deck Pour #12. The rebar subcontractor was onsite to continue installing rebar for Deck Pour #15.
 
Over the next several weeks, the contractor is scheduled to pour concrete for Deck Pour #15, place formwork for Deck Pour #16 in the plaza, continue work related to Gate F, and to complete punch list items related to the Gate G opening.

Project Update

January 18, 2019: This week work on the Gate F Terminal continued for the contractor and their subcontractors. The contractor continued building and installing stairs and handrails and also continued to tighten the bolts on the fenders on the Gate F float. The contractor's crews began installing stiffeners in the hull of the float.  The electrical subcontractor continued working on the electrical cabinets on the float, while the electronics subcontractor began working on the motor on the sliding doors and the key card reader on the portal. One of the electrical subs began installing the Clipper card readers on the Gate F float. The metal subcontractor continued installing handrail on the Gate F float and promenade, while the carpentry subcontractor continued installing, sanding, and staining the wood top rail. In the lagoon, the contractor continued setting side forms, aluma beams, and plywood for Deck Pour #15 and the subcontractor began installing rebar for Deck Pour #15.
 
Over the next several weeks, the contractor and subcontractor are scheduled to install formwork for Deck Pour #15 and Deck Pour #16 for the plaza, install rebar for Deck Pour #15, continue work related to Terminal F operation, and complete punch list items related to Terminal G.

Project Update

January 11, 2019: This week work on Gate F continued as the contractor began building and installing stairs and handrails on the float, and also continued to tighten the bolts on the fenders. The metal subcontractor continued installing handrail on the Gate F float, while the carpentry subcontractor began installing the wood top rail. At the Gate F portal, the metal subcontractor continued the installation of architectural metal. In the lagoon, the contractor began setting falsework beams, aluma beams, and plywood for Deck Pour #15, and the crew continued striping the forms from Deck Pour #14.

Over the next several weeks, the contractor is scheduled to install formwork for Deck Pour #15 for the plaza, continue work related to completing Gate F.

Stay Informed / Contact Us

Keep up to date on the project’s progress through any of the channels below or contact us at weta_ftx@watertransit.org.

WETA-FTX 
Sign up for
email updates
WETA-FTX 
WETAFTXproject
WETA-FTX 
@weta_ftx
WETA-FTX 
weta_ftx