Project Update
October 26, 2018: This week the contractor finished placing the shut out formwork and the beam formwork for Deck Pour #14 and the rebar subcontractor finished placing reinforcement. Deck Pour #14 was successfully completed during a night pour. Waterside of Gate F, the contractor continued work on production piles for the last 3 guide piles for the Gate F float. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp for Pour #7 and continued demolition, and the subcontractor placed reinforcement. On the promenade, the subcontractors continued to place granite at Gate F, continued to place formwork for the containment curb, started to install the curbed guardrail, and placed waterproofing and completed the pour for the south-most topping slab area.
Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install pipe for fireline, and continue with installation of the various portal components and guide and fender piles at terminal Gate F. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue installation of the promenade topping slab and containment bands, begin installation of portal roofing and waterproofing, and begin installation of interim power and communication.