November 16, 2018: This week, in the lagoon, the contractor continued stripping the soffit forms and alumna beams from Deck Pour #10 and Deck Pour #11, while also removing soil from the electrical line trench in the north lay down area. Waterside of Gate G, the contractor installed the float and attached the gangway, while the metal subcontractor continued to install architectural metal for the portal. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp, stairs, and landing for Pour #7. On the promenade, the subcontractors continued to place reinforcement for the topping slab, to place drainage fabric, and to install joints and diamond dowels for the topping slab. The concrete subcontractor also finished pouring the promenade topping slab. The glazing subcontractor was on site this week to begin the installation of the canopy glazing.
Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install the float and gangway at Gate F, and continue with installation of the various portal components at terminal Gate F. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue the installation of the canopy glazing, begin installation of portal roofing and waterproofing, and continue installation of interim power and communication.