The Downtown San Francisco Ferry Terminal Expansion Project

Project Home | Background | Environmental Review | Construction | Outreach | Updates

Project Update

February 8, 2019: This week work on Gate F continued, including power washing and cleaning the float and gangway and touchup paint on the piles, pile collars, float, gangway, fenders on the Gate F float, and the promenade canopy. The electrical sub completed their last installations of lights on the Gate F Portal, while the contractor finished installing stainless corner pieces on the Gate F Portal pedestal. The glazing subcontractor was onsite installing waterproofing on the promenade canopy. The metal subcontractor continued to install soffit panels on the Gate F and Gate G Portal Canopies. The paint subcontractor was onsite to paint the traditional handrail on the promenade. In the lagoon, the contractor began installing the falsework for Deck Pour #16.

Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, and completing punchlist items related to the Section 1 opening.

Project Update

February 8, 2019: This week work on Gate F Terminal continued, including sanding and staining the top rails on the float and gangway and paint touch-ups on the pile collars and fenders. Additionally, the electrical subcontractor began installing conduit in the portal canopy at Gate G for the electronic real-time sign, the glazing subcontractor was onsite installing waterproofing on the promenade canopy, and the metal subcontractor continued to install soffit panels on the Gate F portal and began preparations for the install of soffit panels on the Gate G portal. In the lagoon, the contractor began installing the falsework for Deck Pour #16.
 
Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, continue work related to opening Gate F, and continue work on the punch list items related to the opening of the promenade.

Project Update

February 1, 2019: This week work on Gate F continued as the contractor began sanding and staining the top rails on the float and gangway and the electrical sub began installing conduit in Deck Pour #15 for the light posts in the lagoon. The glazing subcontractor was onsite installing waterproofing on the promenade canopy and the metal subcontractor installed the letters on the Gate F portal and began the installation of the portal canopy soffit panels. In the lagoon, the rebar subcontractor was onsite to continue installing rebar for Deck Pour #15, and the contractor successfully poured Deck Pour #15.
 
Over the next several weeks, the contractor is scheduled to place formwork for Deck Pour #16 in the plaza, pour concrete for Deck Pour #16, continue work related to Terminal F operational, and completing punch list items related to Gate G gangway and float.

Project Update

January 25, 2019: This week work continued on Gate F as the contractor began tack welding the pins on the gangway bushing plates, installing electrical equipment in the electrical cabinets and installing, sanding, and staining the wood top rail. The metal subcontractor also began installing the letters on the Gate F portal canopy and began prepping the portal canopy soffit panels for installation. In the lagoon, the contractor continued setting side forms Deck Pour #15, while also stripping soffit forms from Deck Pour #12. The rebar subcontractor was onsite to continue installing rebar for Deck Pour #15.
 
Over the next several weeks, the contractor is scheduled to pour concrete for Deck Pour #15, place formwork for Deck Pour #16 in the plaza, continue work related to Gate F, and to complete punch list items related to the Gate G opening.

Project Update

January 18, 2019: This week work on the Gate F Terminal continued for the contractor and their subcontractors. The contractor continued building and installing stairs and handrails and also continued to tighten the bolts on the fenders on the Gate F float. The contractor's crews began installing stiffeners in the hull of the float.  The electrical subcontractor continued working on the electrical cabinets on the float, while the electronics subcontractor began working on the motor on the sliding doors and the key card reader on the portal. One of the electrical subs began installing the Clipper card readers on the Gate F float. The metal subcontractor continued installing handrail on the Gate F float and promenade, while the carpentry subcontractor continued installing, sanding, and staining the wood top rail. In the lagoon, the contractor continued setting side forms, aluma beams, and plywood for Deck Pour #15 and the subcontractor began installing rebar for Deck Pour #15.
 
Over the next several weeks, the contractor and subcontractor are scheduled to install formwork for Deck Pour #15 and Deck Pour #16 for the plaza, install rebar for Deck Pour #15, continue work related to Terminal F operation, and complete punch list items related to Terminal G.

Project Update

January 11, 2019: This week work on Gate F continued as the contractor began building and installing stairs and handrails on the float, and also continued to tighten the bolts on the fenders. The metal subcontractor continued installing handrail on the Gate F float, while the carpentry subcontractor began installing the wood top rail. At the Gate F portal, the metal subcontractor continued the installation of architectural metal. In the lagoon, the contractor began setting falsework beams, aluma beams, and plywood for Deck Pour #15, and the crew continued striping the forms from Deck Pour #14.

Over the next several weeks, the contractor is scheduled to install formwork for Deck Pour #15 for the plaza, continue work related to completing Gate F.

Project Update

December 28, 2018: This week the contractor began installing the posts for the lights that will be mounted onto the fenders of the Gate F float. The electrical subcontractor continued installing conduit on the float while also pulling wire from the Gate F portal to the Gate F float. Work continued on the promenade as the contractor continued the installation of benches and the metal subcontractor began the installation of handrails on the west side of the promenade. Over the next several weeks, the contractor is scheduled install formwork for Deck Pour #15 for the plaza and continue work to complete Gate F.

Project Update

January 4, 2019: This week, the contractor and their subcontractors continued work on Gate F. The contractor continued installing the transition ramps from the gangway to the float and tightening the bolts on the pile collars on the Gate F Float. The electrical subcontractor continued installing conduit on the float and the metal subcontractor began the installation of the traditional handrails on the west side of the promenade and continued installing handrail on the Gate F Float.  The Gate F Portal work also continued with the installation of architectural metal. In the lagoon, the contractor began setting falsework beams for Deck Pour #15, while striping the forms from Deck Pour #14.
 
Over the next several weeks, the contractor is scheduled to install formwork for Deck Pour #15, complete the form removal from Deck Pour #14, continue work related to Gate F, and complete punch list items for Gate G.

Project Update

December 21, 2018: This week Gate G opened to the public for ferry service.  Other big news this week was the arrival of the Gate F float and gangway to the project site. Work continued along the promenade this week including the installation of benches, finishing the glazing on the promenade canopy and installation of the traditional handrails.  Crews also continued with installation of architectural metal and control wiring for the Gate F portal doors.

Over the next several weeks, the contractor is scheduled install formwork for Deck Pour #15 for the plaza, continue work on Gate F and complete punchlist items for Gate G.

Project Update

December 14, 2018: This week the contractor continued installing the float and gangway accessories for Gate G, including light fixtures, automatic sliding doors, and security cameras. The concrete subcontractor began power washing the concrete on the promenade, sawcutting joints into the curb near the ramp, and patching the stairs. The metal subcontractor continued installation of Gate G portal architectural metal, and began installing the seismic joint handrail at both ends of the pedestrian bridge. The waterproofing subcontractor placed caulking for the joints in the south laydown area and the installation of the canopy glazing continued.
 
Over the next several weeks, Gate G is scheduled to open to the public.  The contractor will also continue to install formwork for Deck Pour #15, install the float and gangway at Gate F, and install various portal components and site furnishings. Subcontractors are scheduled to install rebar for Deck Pour #15, and continue the installation of the canopy glazing, portal roofing/ waterproofing, electrical and communication components, and railings and site furnishings.

Stay Informed / Contact Us

Keep up to date on the project’s progress through any of the channels below or contact us at weta_ftx@watertransit.org.

WETA-FTX 
Sign up for
email updates
WETA-FTX 
WETAFTXproject
WETA-FTX 
@weta_ftx
WETA-FTX 
weta_ftx