The Downtown San Francisco Ferry Terminal Expansion Project

Project Home | Background | Environmental Review | Construction | Outreach | Updates

Project Update

October 11, 2019: This week the granite subcontractor continued placing mortar and granite blocks for the seating area to the North of the mockup area. The granite subcontractor also placed the setting bed and crack suppression membrane on the North side of the plaza and continued placing granite for the Gate E Portal. The contractor continued adjusting formwork for the bolster beams along with stripping soffit forms from the South end of Deck Pour #20. The contractor also began setting the catch basins within Deck Pour #21. This week the contractor successfully placed concrete for Deck Pour #22 while also placing sika near the east most set of stairs on the North side of the plaza. The metal subcontractor continued work on the Gate E portal while also working on the seismic joint embed extensions on the North side of the plaza. The concrete subcontractor continued placing side forms for the promenade curb and the containment edge on the Deck Pour #14 ramp. The glazing subcontractor continued working on the promenade canopy in preparation for glazing and the gutters to be installed.
 
Over the next several weeks, the contractor and their subcontractors are scheduled to place dowels, rebar, and concrete for Deck Pour #21, install the promenade canopy glazing, install the Gate E portal electrical and granite, pour the bolster beam, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.

Project Update

September 27, 2019: This week, the granite subcontractor continued placing mortar and granite blocks for the seating area to the North of the mockup area, placed the setting bed and crack suppression membrane in the Northwest corner of the plaza, and continued to drill dowel holes within Deck Pour #12 for the granite blocks. The contractor began stripping the soffit forms from Deck Pour #20 while also installing formwork, drilling and dowelling of rebar for the bolster beams. This week the metal subcontractor placed the Gate E door frame, continued work on the promenade canopy, installing the handrail extensions for the stairs on the West side of the plaza and installing embed extensions on the North side of the plaza.

Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #22, place dowels, rebar, and concrete rebar for Deck Pour #21, install the promenade canopy glazing, install the Gate E portal electrical and granite, pour the bolster beam, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.

Project Update

September 20, 2019: This week, the granite subcontractor continued placing mortar and granite blocks for the seating area to the North of the mockup area. The granite subcontractor also placed the setting bed and crack suppression membrane on the second set of stairs on the West side of the plaza. The contractor continued installing formwork for the bolster beams along with the side forms and formwork for Deck Pour #22. The contractor also placed concrete for the Gate E portal pedestals. This week the metal subcontractor, with the assistance of the contractor, set the promenade canopy and the Gate E portal. The metal subcontractor also began the installation of the handrail extensions at the stairs on the West side of the plaza and continued the installation on embed extensions in the Northwest corner of the plaza.

Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #21 and Deck Pour #22, install rebar for Deck Pour #22, place dowels and rebar for Deck Pour #21, install the promenade canopy glazing, install the Gate E portal electrical and granite, pour the bolster beam, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.

Project Update

September 13, 2019: This week the granite subcontractor continued placing mortar and granite pavers for the mockup area on the top of the plaza and along the lower step. The granite subcontractor also placed the setting bed on the West side of the plaza, while also placing granite cladding around the light pedestal. The contractor continued the installation of side forms and formwork for Deck Pour #22. The contractor also began installing formwork for the bolster beams. The rebar subcontractor began installing rebar for the bolster beams that run underneath Deck Pour #21, while also installing rebar for the Gate E portal pedestals. The waterproofing subcontractor was onsite to install the stego wrap and J-drain on the Northwest corner of the plaza.
 
Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #21 and Deck Pour #22, install formwork and rebar for Deck Pour #22, place dowels and rebar for Deck Pour #21, install the promenade canopy, install the Gate E portal, pour the Gate E pedestals, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.

Project Update

September 6, 2019: This week the granite subcontractor continued placing mortar and granite pavers for the mockup area on the top of the plaza and along the lower step. The granite subcontractor also placed their setting bed and crack suppression membrane on the lower step of the west side of the plaza. The contractor continued the installation of side forms for Deck Pour #23, while also installing the trench drains, area drains, and portal embed bolts. The contractor also prepared for the concrete placement for Deck Pour #20 and Deck Pour #23 by cleaning debris off the deck of both pours, installing block outs for the promenade canopy, and closing the trench drains with plywood and duct tape. The rebar subcontractor finished installing rebar for Deck Pour #20 and Deck Pour #23. The electrical subcontractor finished installing electrical and communications conduit within Deck Pour #23. The contractor successfully placed concrete for Deck Pour #20 and Deck Pour #23.
 
Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #21 and Deck Pour #22, install formwork and rebar for Deck Pour #22, place dowels and rebar for Deck Pour #21, install the promenade canopy, install the Gate E portal, pour the Gate E pedestals, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.

Project Update

August 30, 2019: This week the granite subcontractor continued placing mortar and granite blocks for the mockup area for the seating and planter walls. The granite contractor also placed the crack suppression membrane on the top of the plaza mockup area. The contractor continued stripping the side forms from Deck Pour #12 and Deck Pour #13. The contractor also continued drilling holes for dowels on the topside of Deck Pour #21, while also installing side forms for the South side of Deck Pour #21. The contractor continued the installation of side forms for Deck Pour #23, while also installing the catch basins, area drains, and portal embeds. The rebar subcontractor continued installing rebar for the Deck Pour #20 curb and deck, while also installing rebar for Deck Pour #23. The electrical subcontractor continued installing electrical and communications conduit within Deck Pour #20, while also installing electrical and communications conduit for Deck Pour #23. The contractor also began placing formwork for Deck Pour #22 while also adjusting the falsework beams.

Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #20 and Deck Pour #23, install formwork and rebar for Deck Pour #22, place dowels and rebar for Deck Pour #21, install the promenade canopy, continue the install of granite for the mockup area and the West amphitheater seating, continue the refurbishment of the Gate E Float, and complete punch list items related to Section 1.

Project Update

August 23, 2019: This week the granite subcontractor continued placing mortar and granite blocks for the mockup area. The contractor began stripping the side forms from Deck Pour #12 and Deck Pour #13. The contractor also continued drilling holes for dowels on the topside of Deck Pour #21, while also installing side forms for the South side of Deck Pour #21. The rebar subcontractor continued installing rebar for the Deck Pour #20 curb and deck. The electrical subcontractor began installing electrical and communications conduit within Deck Pour #20, while the plumbing subcontractor installed the water line within Deck Pour #20. The contractor continued the installation of formwork for Deck Pour #23, while also installing plywood and side forms. This week, the contractor also drove the 5 barrier piles along the North side of Pier 14.

Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #20 and Deck Pour #23, place dowels and pour concrete for Deck Pour #21, continue the install of granite for the mockup area, continue the refurbishment of the Gate E Float, and complete punch list items related to Section 1.

Project Update

August 16, 2019: This week, the granite subcontractor continued the placement of mortar and granite blocks. The waterproofing subcontractor began installing waterproofing on the top section of the plaza. The contractor successfully placed concrete for the stepped seating in Deck Pour #12 and the slab in Deck Pour #13 during a night pour. The contractor began installing the dowels in Deck Pour #21 and continued installing side forms for the South side of Deck Pour #21. The rebar subcontractor continued installing rebar for the Deck Pour #20 canopy beam and deck. The contractor began installing catch basins and trench drains within Deck Pour #20, while also installing the promenade canopy embeds within the canopy beam. The contractor continued installing the falsework beams for Deck Pour #23, while also beginning the installation of formwork for Deck Pour #23.
 
Over the next several weeks, the contractor and their subcontractors are scheduled to place rebar and concrete for Deck Pour #20 and Deck Pour #23, place dowels, rebar, and formwork for Deck Pour #21, install falsework and formwork for Deck Pour #22, continue the install of granite for the mockup area, continue the refurbishment of the Gate E Float, and drive barrier piles along Pier 14.

Project Update

August 9, 2019: This week, the granite subcontractor continued the placement of mortar and granite blocks for the mockup area. The contractor began fitting the embeds for the bioretention planter walls around Deck Pour #12 and Deck Pour #13 and continued drilling holes for dowels in the underside of Deck Pour #21 for the bolster beam, while also installing the dowels and epoxy. The contractor also placed concrete in the remaining Deck Pour #23 piles and the Deck Pour #14 planter walls. The rebar subcontractor continued installing rebar for Deck Pour #12 and Deck Pour #13 deck and steps. Following the completion of the rebar for Deck Pour #12 and Deck Pour #13 the rebar subcontractor began installing rebar for Deck Pour #20. The pile driving crew drove the two remaining fender piles at Gate E, the electrical subcontractor continued installing the promenade canopy lights, and the contractor continued installing formwork and pony walls for Deck Pour #20, while beginning the falsework for Deck Pour #23.

Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #12 and #13, continue installing rebar for Deck Pour #20, place dowels and pour concrete for Deck Pour #21, continue the install of granite for the mockup area, continue the refurbishment of the Gate E Float, drive barrier piles along Pier 14, and complete punch list items related to Section 1.

Project Update

July 26, 2019: This week, the granite subcontractor began the placement of mortar and granite blocks. The concrete subcontractor started the accent band at the planter wall in the mock-up area, and the metal works subcontractor finished raising the seismic embed elevation in the mock-up area. The contractor continued to drill holes in the existing concrete slab for the dowels within Deck Pour #21, to install falsework and formwork at Pour #20, and to install falsework for the bolster beams. The contractor installed the pile template and vibrated the last three guide piles for Gate E.

Over the next several weeks, the granite contractor will continue the installation of granite, the rebar subcontractor is scheduled to complete the rebar within Deck Pour #12 and #13, the metal works subcontractor is scheduled to continue work on the seismic embed, and the contractor is scheduled to install falsework and formwork for Deck Pour #20, and install formwork and pour concrete for Deck Pour #21. The contractor will continue the refurbishment of the Gate E Float off-site, drive fender and barrier piles, and complete punch list items related to Section 1.

 

Stay Informed / Contact Us

Keep up to date on the project’s progress through any of the channels below or contact us at weta_ftx@watertransit.org.

WETA-FTX 
Sign up for
email updates
WETA-FTX 
WETAFTXproject
WETA-FTX 
@weta_ftx
WETA-FTX 
weta_ftx