The Downtown San Francisco Ferry Terminal Expansion Project

Project Home | Background | Environmental Review | Construction | Outreach | Updates

Project Update

November 30, 2018: This week the contractor continued with the installation of the float and gangway, while subcontractors began installing the electrical and communication on the float. The contractor also drove the last of the piles for this driving season and installed the donut fenders on the piles. The architectural metal installation continued at both portals, while the portal waterproofing installation began. On the promenade, the installation of the canopy glazing support brackets continued, while the installation of glazing began.
 
Over the next several weeks, the contractor is scheduled to install formwork for deck pour #15, install the float at Gate F, and continue with the installation of the various portal components. Subcontractors are scheduled to install rebar for deck pour #15, continue the installation of the canopy glazing, continue installation of portal roofing/ waterproofing, and continue the installation of electrical and communication components.

Project Update

November 23, 2018: This week the contractor continued stripping the formwork in the lagoon from concrete Deck Pour #10 and Deck Pour #11. On the waterside of Gate G, the contractor continued with the installation of the float and gangway. The architectural metal installation continued a both portals, while the portal water proofing installation began. In the south lay down area, the contractor placed concrete for the pedestrian bridge landing, stairs and ramp. On the promenade, the installation of the canopy roof glazing support brackets continued.

Over the next several weeks, the contractor is scheduled to form concrete Deck Pour #15, install the float at Gate F, and continue with installation of the various portal components. Subcontractors are scheduled to install rebar for Deck Pour #15, continue the installation of the canopy glazing, begin installation of portal roofing/waterproofing, and continue the installation of electrical and communication components.

Project Update

November 16, 2018: This week, in the lagoon, the contractor continued stripping the soffit forms and alumna beams from Deck Pour #10 and Deck Pour #11, while also removing soil from the electrical line trench in the north lay down area. Waterside of Gate G, the contractor installed the float and attached the gangway, while the metal subcontractor continued to install architectural metal for the portal. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp, stairs, and landing for Pour #7. On the promenade, the subcontractors continued to place reinforcement for the topping slab, to place drainage fabric, and to install joints and diamond dowels for the topping slab. The concrete subcontractor also finished pouring the promenade topping slab. The glazing subcontractor was on site this week to begin the installation of the canopy glazing.

Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install the float and gangway at Gate F, and continue with installation of the various portal components at terminal Gate F. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue the installation of the canopy glazing, begin installation of portal roofing and waterproofing, and continue installation of interim power and communication.

Project Update

November 9, 2018: This week, in the lagoon, the contractor continued stripping the soffit forms and aluma beams from Deck Pour #10 and Deck Pour #11, while also removing the cold joint forms from the end of Deck Pour #14. At Gate G, the contractor installed the gangway, while the metal subcontractor began to install architectural metal for the portal. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp, stairs, and landing for Pour #7. On the promenade, the subcontractors continued to place drainage fabric, reinforcement, and joist and diamond dowels for the topping slab. The electrical subcontractor began pulling wire from the Agriculture Building to the electrical cabinets on the promenade.

Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install the float at Gate G, and continue with installation of the various portal components at terminal Gate F and G. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue installation of the promenade topping slab, continue installation of architectural metal and waterproofing, and continue installation of temp power and communication.

Project Update

November 2, 2018: This week, in the lagoon, the contractor began stripping the side forms from Deck Pour #14. Waterside of Gate F, the contractor finished driving the piles for the Gate F float. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp for Pour #7. On the promenade, the subcontractors continued to place reinforcement in the containment curb, continued to place formwork for the containment curb, continued to install the curbed guardrail, and completed the pour of the remaining containment curbs. The electrical subcontractor tied into the AG Building electrical panels for power.
 
Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install the float and gangway at Gate G, and continue with installation of the various portal components at terminal Gate F. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue installation of the promenade topping slab, begin installation of portal roofing and waterproofing, and continue installation of interim power and communication.

Project Update

October 26, 2018: This week the contractor finished placing the shut out formwork and the beam formwork for Deck Pour #14 and the rebar subcontractor finished placing reinforcement.  Deck Pour #14 was successfully completed during a night pour. Waterside of Gate F, the contractor continued work on production piles for the last 3 guide piles for the Gate F float. In the south lay down area, the contractor continued to place forms for the landing and wheelchair ramp for Pour #7 and continued demolition, and the subcontractor placed reinforcement. On the promenade, the subcontractors continued to place granite at Gate F, continued to place formwork for the containment curb, started to install the curbed guardrail, and placed waterproofing and completed the pour for the south-most topping slab area.
 
Over the next several weeks, the contractor is scheduled to form the landing and wheelchair ramp for Pour #7 and Deck Pour #15, install pipe for fireline, and continue with installation of the various portal components and guide and fender piles at terminal Gate F. Subcontractors are scheduled to place rebar for Pour #7 and Deck Pour #15, continue installation of the promenade topping slab and containment bands, begin installation of portal roofing and waterproofing, and begin installation of interim power and communication.

Project Update

October 19, 2018: This week the contractor continued with the removal of concrete formwork and falsework from Deck Pour #10 and installation of falsework beams and plywood for Deck Pour #14 and Deck Pour #15. Waterside of Gate F, the contractor drove the first 3 guide piles for the Gate F float. In the south lay down area, the contractor began to place forms for the landing and wheelchair ramp for Pour #7 and continued demolition. The contractor also began saw cutting the fire waterline trench on the Embarcadero side of the fence, outside of the south lay down area. On the promenade, the granite subcontractor continued to place granite at Gate F and began to seal the granite at Gate G.  Also on the promenade, the concrete subcontractor continued placing formwork for the containment curb and finished placing concrete for the south-most containment band.
 
Over the next several weeks, the contractor is scheduled to pour Deck Pour #14, continue installing the falsework in the middle of the lagoon, and continue with installation of the various portal components and guide and fender piles at terminal Gate F and Gate G. Subcontractors are scheduled to place rebar for Deck Pour #7 and Deck Pour #15, begin installation of the promenade topping slab, and begin installation of interim power and communication.

Project Update

October 12: This week the contractor continued with the removal of concrete formwork and falsework from Deck Pour #10 and continued installation of falsework beams and plywood for Deck Pour #14 and Deck Pour #15. At Deck Pour #14, the rebar subcontractor began placing reinforcement and the electrical subcontractor began placing conduit on the bottom mat of rebar. Waterside of Gate G, the contractor drove the remaining 3 guide piles for the Gate G float. On the promenade, the contractor began placing granite at Gate F and installing drains on the canopy roof. Also on the promenade, subcontractors began placing formwork for the containment curb, while the contractor began placing dowels for the containment curb.

Over the next several weeks, the contractor is scheduled to pour Deck Pour #14, begin installing the falsework in the middle of the lagoon, and continue with installation of the various portal components at terminal Gate F and Gate G. Subcontractors are also scheduled to place rebar for Deck Pour #14 and Deck Pour #15, begin installation of the promenade topping slab, and finish patching the promenade curb concrete.

Project Update

October 5, 2018: This week the contractor continued with the removal of concrete formwork and falsework from Deck Pour #9 and Deck Pour #10 and continued installation of falsework beams and plywood for Deck Pour #14. In the south lay down area, the contractor also placed formwork and side forms in preparation for Pour #7 and the rebar subcontractor began placing reinforcement. The contractor assisted one of their subcontractors in placing the promenade canopy, and the three pieces of the promenade canopy were welded together. At the promenade terminal Gate F, subcontractors began the installation of granite cladding. One of the subcontractors began placing formwork for the containment curb on the promenade deck.  

Over the next several weeks, the contractor is scheduled to continue installing the falsework and formwork in the lagoon along the AG Building, begin installing the falsework in the middle of the lagoon, and continue with installation of the various portal components at terminal Gate F and Gate G. Subcontractors are also scheduled to place rebar for Deck Pour #14 and Deck Pour #15, begin installation of the promenade topping slab, and finish patching the promenade curb concrete.

Project Update

September 28, 2018: This week the contractor continued with the removal of concrete formwork and falsework from Deck Pour #9 and Deck Pour #10 and continued installation of falsework beams and plywood for Deck Pour #14. In the south laydown area, the contractor also began the demolition work in preparation for Pour #7. At the promenade terminal Gate G, subcontractors continued with the installation of granite cladding. The contractor also began driving float guide piles for Gate G.
 
Over the next several weeks, the contractor is scheduled to continue installing the falsework and formwork in the lagoon along the AG Building, begin installing the falsework in the middle of the lagoon, and continue with installation of the various portal components at terminal Gate F and Gate G. Subcontractors are also scheduled to place rebar for Deck Pour #14 and Deck Pour #15, begin installation of the promenade topping slab, and finish patching the promenade curb concrete.

Stay Informed / Contact Us

Keep up to date on the project’s progress through any of the channels below or contact us at weta_ftx@watertransit.org.

WETA-FTX 
Sign up for
email updates
WETA-FTX 
WETAFTXproject
WETA-FTX 
@weta_ftx
WETA-FTX 
weta_ftx