Project Update
May 24, 2019: This week the contractor began lowering and stripping soffit forms and removing the cold joint forms on the north and east sides of Deck Pour #19 . The crew also began roughening the surfaces of the concrete revealed from the removal of the cold joint forms in preparation for future concrete pours. The granite contractor was onsite laying out chalk lines for the placement of dowels for granite install. The granite crew also continued drilling holes for the dowels that will be installed in the steps on the North side of the plaza. Work was done to install the side forms for the remainder of the walls within Deck Pour #14 and to install the falsework for Deck Pour #12 and Deck Pour #13. The crew also continued demolition of concrete and granite on the East side of the existing Gate E.
Over the next several weeks, the contractor is scheduled to continue to place formwork for Deck Pour #13, continue the demo of concrete that is in Deck Pour #13, pour concrete for Deck Pour #21, begin the install of granite for the mockup area, and complete punch list items related to Section 1.