Project Update
October 25, 2019: This week the granite subcontractor continued placing mortar and granite blocks for the seating area and landing on the north side of the plaza. The granite subcontractor also installed waterproofing on the top of the plaza along the planter. The waterproofing subcontractor applied waterproofing on the plaza and the north amphitheater stepped seating, so that the granite subcontractor could install the setting bed on the north steps. The contractor prepared for Deck Pour #21 by installing side forms, drilling holes for the dowels, and placing the epoxy and dowels. The contractor continued demo at the seawall and install of wave baffle forms, and continued demo at the north driveway. This week the rebar subcontractor began installing the rebar for the east side of Deck Pour #21, which will be done in two parts. The concrete subcontractor worked to install the containment band formwork on Deck Pour #20.
Over the next several weeks, the contractor and their subcontractors are scheduled to place dowels, rebar, and concrete for Deck Pour #21, install the promenade canopy glazing, install the Gate E portal electrical and granite, continue the refurbishment of the Gate E Float, continue installing granite for the mockup area and the West amphitheater seating, and complete punch list items related to Section 1.