Project Update
January 10, 2020: Work continued this week to complete the install of the Gate E portal: the automated services subcontractor continued to work on programing the portal doors and the electrical subcontractor continued to work on wiring at the Gate E portal.
In the Plaza, the granite subcontractor continued installing granite on the south planter walls and another crew continued installing pavers in the middle of the plaza. The crew also worked to install granite on the north side of the bioretention walls. The waterproofing subcontractor placed their next section of waterproofing on the plaza and placed water proofing in the bioretention planter.
The contractor continued installing the seismic joint embeds on the Ferry Building side while demolishing the existing topping slab along the Bart driveway. The contractor continued building and installing forms for the wave baffle. The contractor also continued stripping side forms from the second half of Deck Pour #21. This week, the water subcontractor continued installing the water connection for the Section 2 area. The rebar subcontractor continued the installation of rebar for the wave baffle. All the while the metal subcontractor began installing the traditional railing on top of the south wall and began the process of installing the guardrail on top of the plaza.
Over the next several weeks, the contractor and their subcontractors are scheduled to place rebar, and concrete for the wave baffle, install the promenade canopy glazing end caps and caulking, install the Gate E portal electrical and communications, continue installing granite on the plaza, the bioretention planter, and the South planter, continue work on the Gate E float and gangway, continue installing guardrail and handrail, and complete punch list items related to Section 1.