The Downtown San Francisco Ferry Terminal Expansion Project

Project Home | Background | Environmental Review | Construction | Outreach | Past Updates

Project Update

February 16: This week the contractor removed the falsework supporting the promenade deck concrete pour #2 and began reinstalling it for promenade deck pour #5 at the new Gate G location. The contractor also placed concrete for promenade deck pour #3. Over the next several weeks the contractor is scheduled to place concrete in piles at the lagoon, install more scaffolding on the lagoon piles, install falsework/formwork at promenade deck pour #5 and install formwork for lagoon deck pour #8.

Project Update

February 9: This week the contractor began to strip forms from the promenade deck concrete pour #2, placed concrete in piles located in the southwest corner of the lagoon, placed concrete for the promenade canopy beam and continued installation of concrete embeds in preparation for the promenade concrete deck pour #3. Over the next several weeks the contractor is scheduled to continue work onsite installing concrete deck embeds, rebar, utilities conduits and placing concrete for the promenade deck, while offsite metals fabrication will continue for the new terminal floats.

Project Update

February 1: This week the contractor continued installing the side forms for the future promenade deck concrete pours, finished installing the rebar mats for the promenade canopy beam, and began installing the bottom mat for deck pour #3. The contractor also began installing embeds for the promenade canopy structure and the pedestrian bridge seismic joint. Meanwhile, metal plates are being cut offsite in preparation for fabricating the new terminal floats and gangways. Over the next several weeks the contractor is scheduled to continue installing concrete deck embeds, rebar, placing concrete for the promenade deck while continuing to cut metal for the terminal floats/gangway fabrication.

Project Update

January 26: The contractor continued to construct the promenade deck falsework and formwork to support the construction of the new concrete deck moving near the future Gate F terminal. They also began installing the rebar for the promenade deck canopy beam and completed placement of the first reinforced concrete deck section for the promenade. In preparation for future work additional rebar, falsework and scaffolding was delivered to the project. Over the next several weeks the contractor’s crews are scheduled to continue installing promenade deck falsework/formwork, install concrete deck embeds/rebar, install pile rebar cages in the lagoon area, place concrete for the promenade canopy beam and place concrete for the next section of promenade deck.

Project Update

January 18: This week the contractor continued installing the side forms for the promenade canopy beam and finished installing the rebar mats for the first deck pour which is scheduled for the middle of next week. The contractor also continued forming what will be the foundation for the false work to support the promenade deck moving north toward the lagoon. The contractor successfully completed a day shift pile concrete pour in which 14 piles were filled with concrete. Over the next several weeks the contractor’s crews are scheduled to continue installing concrete deck embeds, rebar, and prepare for the upcoming promenade deck pours.

Project Update

January 12: This week the contractor began installing the side forms and rebar mats in preparation for the first promenade deck concrete pour which is scheduled for next week. The contractor also continued forming false work that will support the promenade deck moving north toward the lagoon. Scheduled for next week are both a day shift concrete pile pour and the first night shift concrete deck pour. Over the next several weeks the contractor’s crews are scheduled to continue installing concrete deck embeds and rebar.

Project Update

January 5: This week the contractor began installing the side forms for the first deck pour, the Aluma beam system that will support the promenade canopy beam and began to lay down plywood falsework upon which the promenade canopy beam will be poured. The contractor also laid out the catch basins and trench drains that will be embedded in the first promenade deck pour. Over the next several weeks the contractor’s crews are scheduled to begin installing concrete deck embeds, rebar, and prepare for the first promenade deck pour.

Project Update

December 29: This week there was no work performed onsite. Starting in the new year, the contractor’s crews are scheduled to begin installing concrete deck embeds, rebar, and prepare for the first promenade deck concrete pour.

Project Update

December 22: This week the contractor continued to form the beam system that will support the promenade deck during upcoming concrete pours. The crews continued to lay down plywood, and began filling in the formwork gaps around the piles with foam. The contractor is not planning to work next week but will be back to work on January 2nd, 2018. Starting in the new year, the contractor’s crews are scheduled to begin installing concrete deck embeds, rebar, and prepare for the first promenade deck pour.

Project Update

December 15: This week the contractor finished stripping the soffit forms from the recently poured pedestrian bridge concrete pile caps. The crews began disassembling the beam system that held the form work up over the water. The contractor continued to install rebar cages and I-beams into the Promenade deck foundation piles on the east side of the Agricultural Building. The crew also successfully completed a small concrete pour in which 10 promenade foundation piles were filled. Over the next few weeks the contractor is scheduled to begin installing rebar and embeds for the Promenade deck, continue installing falsework hangers and scaffolding on piles, continue setting rebar cages and I-beams into the promenade foundation piles, and start preparing for the upcoming day time promenade pile pours and the nighttime pours for the new promenade deck.

Stay Informed / Contact Us

Keep up to date on the project’s progress through any of the channels below or contact us at weta_ftx@watertransit.org.

WETA-FTX 
Sign up for
email updates
WETA-FTX 
WETAFTXproject
WETA-FTX 
@weta_ftx
WETA-FTX 
weta_ftx