Project Update
August 9, 2019: This week, the granite subcontractor continued the placement of mortar and granite blocks for the mockup area. The contractor began fitting the embeds for the bioretention planter walls around Deck Pour #12 and Deck Pour #13 and continued drilling holes for dowels in the underside of Deck Pour #21 for the bolster beam, while also installing the dowels and epoxy. The contractor also placed concrete in the remaining Deck Pour #23 piles and the Deck Pour #14 planter walls. The rebar subcontractor continued installing rebar for Deck Pour #12 and Deck Pour #13 deck and steps. Following the completion of the rebar for Deck Pour #12 and Deck Pour #13 the rebar subcontractor began installing rebar for Deck Pour #20. The pile driving crew drove the two remaining fender piles at Gate E, the electrical subcontractor continued installing the promenade canopy lights, and the contractor continued installing formwork and pony walls for Deck Pour #20, while beginning the falsework for Deck Pour #23.
Over the next several weeks, the contractor and their subcontractors are scheduled to place concrete and rebar for Deck Pour #12 and #13, continue installing rebar for Deck Pour #20, place dowels and pour concrete for Deck Pour #21, continue the install of granite for the mockup area, continue the refurbishment of the Gate E Float, drive barrier piles along Pier 14, and complete punch list items related to Section 1.